Pakistan

Pakistan's 46,275 MW fleet still leans on thermal generation — around 42 % of energy — while hydropower supplies roughly 11,864 MW, close to a quarter of total capacity. Against an identified potential of about 60,000 MW gross and roughly 41,000 MW technically and economically viable, near-term procurement is dominated by four large schemes now under construction, alongside a long tail of low-head sites on the Punjab canal network.

Key data

Electricity access (WDI)95.6 % (2023)
Installed capacity46,275 MW national total; ~11,864 MW hydropower (Power Division, June 2026)
Hydropower potential~60,000 MW gross; ~41,045 MW technically and economically viable (WAPDA)
Utility / grid operatorNTDC (transmission) · WAPDA (hydropower development) · NEPRA (regulator)
Key factHydropower ~24 % of installed capacity, thermal ~42 % of energy; annual energy import bill about USD 12 billion

Data: World Bank World Development Indicators (EG.ELC.ACCS.ZS, 2023), CC BY 4.0 · IHA country profiles · Power Division / NEPRA.

Hydropower & mini-grid opportunities

The pipeline splits by head. Large, high-capacity schemes use Francis machines — Dasu Stage-I alone calls for six 360 MW Francis turbines — while the Punjab canal network holds roughly 350 MW of low-head potential better suited to Kaplan and tubular (bulb) units, which pass large flows at heads often under 10 m. Kaplan's adjustable runner blades also hold efficiency across the seasonal flow swings typical of irrigation canals. Few markets run gigawatt-scale Francis procurement and sub-10 m canal schemes inside the same cycle; Pakistan does.

Pakistan also has one of the most mature Chinese engineering-contracting ecosystems outside China: Diamer-Bhasha is being built by a joint venture of China Power and the Frontier Works Organisation, and Dasu Stage-I is being delivered by a GE Renewable Energy and PowerChina Zhongnan consortium. In practice that lowers the qualification barrier for Chinese-manufactured electro-mechanical equipment. TCH HYDRO scope: turbine and generator supply. Auxiliary systems are assembled with our manufacturing partners and executed on site with HIER.

Policy & financing updates

  • National target of roughly 20 GW of hydropower capacity by 2030.
  • FY 2025-26 added 1,820.66 MW net, of which 1,663.44 MW came from solar net-metering and 157.22 MW from hydropower.
  • Identified potential is concentrated in the north: Khyber Pakhtunkhwa ~14,000 MW, Gilgit-Baltistan ~11,700 MW, Azad Jammu & Kashmir ~1,300 MW.
  • Diamer-Bhasha (4,500 MW), Dasu (4,320 MW across two stages, Stage-I 2,160 MW targeting generation from December 2027), Mohmand (800 MW) and Tarbela Fifth Extension (1,530 MW) are all under construction.

FAQ

Which turbine type suits Pakistan's canal sites?

Low-head drops on the Punjab irrigation network suit Kaplan and tubular (bulb) units, which pass large flows at heads often below 10 m. Kaplan's adjustable runner blades keep efficiency acceptable as canal flow varies seasonally — a common failure point for fixed-blade machines.

Do you supply large Francis units?

Yes — Francis machines for high-head, high-capacity schemes are within scope, supplied as matched turbine and generator packages. TCH HYDRO scope: turbine and generator supply. Auxiliary systems are assembled with our manufacturing partners and executed on site with HIER.

Can you rehabilitate existing hydropower plants?

Runner replacement, governor and excitation upgrades, and control and protection retrofits are all within scope, with a two-year spare-parts package supplied with each delivery. Send the existing machine's head, flow, rated output and year of commissioning and we will assess the achievable gain.

Sources

A project, a site, drawings to discuss? Talk to us — reply within 48 hours.

Request a quotation
24/7 Engineer Chat
售前咨询 / Presales
⚡

TCHIER Presales Engineer

Hydropower & Renewable Energy
AI O&M Assistant
🔧

TCH Smart O&M Copilot

Africa Hydro · O&M & Operations